The Tata Power-subsidiary, Coastal Gujarat Power Limited (CGPL), is seemingly on track to achieve commissioning of the first two units of its 4,000 MW Mundra UMPP a year ahead of schedule. CGPL has recently concluded the hydro-test for Unit-II successfully, while the same was achieved for the first unit in March 2010.
- Erection of boiler at Unit-I is also nearing completion, while around 80% of the erection work at Unit-II is complete.
- The developer has also achieved boxing up of the turbine generator (TG) for Unit-II. Erection of TG has also commenced at units II and III. Structural fabrication and erection of the TG deck are, presently, in progress at the remaining units.
- Tata Power bagged the Mundra project in 2007 through the international competitive bidding route. The project entails an investment of over Rs 17,000 crore, which is being funded via a debt and equity ratio of 75:25.