Before the Ministry of Power (MoP) suspended all ongoing activities at NTPC's Loharinag Pala HEP, the developer had managed to achieve substantial progress at the project site. Here, a brief summary of the development milestones achieved by the power major:
- Statutory clearances:
--NOC from SPCB
--Clearance from the Ministry of Defence
--Environmental and forest clearance from MoE&F
--Implementation Agreement signed with the Government of Uttarakhand
- Physical progress-Civil works
1. Barrage and desilting chamber
Excavation for river diversion: 100%; desilting chamber arch widening: 100%; inspection shafts excavation: 100%; excavation for barrage: 90%; inlet/outlet tunnels: 80%; concreting of barrage: 24%
2. Formation of approach roads to adits of HRT
Approach road to Dabrani and Gunga Adit: 100%; Approach road to Helgu Adit: 42%
3. Power house and penstock
Surge shaft pilot boring & reaming:100%; adit to surge shaft & pressure shaft: 100%; tail race tunnel: 86%; main access tunnel: 72%; power house pilot excavation: 39%; switchyard: 42%
4. Dabrani and Gunga Adit to Head race tunnel (HRT): 100%
5. HRT excavation: 20%