
- The ministry is of the opinion that the issues raised by the National Board for Wildlife (NBWL) would not have come up if the project were on schedule.
- A helpless NTPC has asserted that the project faces delays because of the excruciatingly slow progress of civil works by the Italian-Thai Development PLC (ITD). The severe cashflow problems faced by ITD and the consequently inadequate mobilization of resources have added to deferral caused by a series of geological and hydrological problems encountered at the project site, according to the power major, arguments that have failed to move the ministry.
- Accordingly, the ministry has now asked the power firm to make all out efforts to resolve the environmental issue and ensure that the project is not delayed further.
- In the wake of present circumstances, however, the project is likely to miss even its latest commissioning deadline of March 2012.
No comments:
Post a Comment