" This blog is a integrated approach towards tracking the Indian power sector
which is evolving, having a great potential with prosperous future."

ALL INDIA INSTALLED CAPACITY

ALL INDIA INSTALLED CAPACITY

Wednesday, February 16, 2011

Changes to NTPC's performance MoU for 2011-12-III: New project implementation schedule


  As a part of its revision to the draft MoU to be signed by the power major, NTPC, with the union government for the year 2011-12, the power ministry has also updated the project implementation schedule expected of the utility for the fiscal.
  • Accordingly, NTPC has to commission the 500 MW Unit-4 of the Simhadri-II TPP by December 2011 to achieve the excellent rating under the Project Implementation performance category.
  • The commissioning schedules of units 2 and 3 of the Sipat-I TPP have also been moved up, to August 2011 and March 2012, respectively, for the highest rating.
  •  It may be mentioned that the utility would merit the very good and good ratings for this parameter, subsequent to one and two month delays, respectively, against the above figures.

No comments:

Post a Comment