The critical land acquisition process at Reliance Power Limited`s (RPL) 4000 MW Krishanpatnam UMPP, being developed by Coastal Andhra Power Limited (CAPL), a wholly owned subsidiary, is progressing only at a snail`s pace.
- Notably, during the course of one month from October to November 2010, the project has seen almost no movement on this front. As a result, about 100 acres of land still remains to be acquired by the company.
- Meanwhile, works pertaining to studies and investigation, engineering, pre-award works, financing are proceeding apace.
- The UMPP was originally planned to sea light of day by September 2013, when the first 800 MW unit was expected to be operational. As things stand now, the project is likely to be fully commissioned by February 2015.