
With the commissioning of the sixth unit, the total installed capacity of the project would stand at 1,820 MW. Stage-I of the project, worth 840 MW, comprises of four units of 210 MW capacity, operational since the early 90s, while the Stage-II expansion envisages setting up of two units of 490 MW capacity, each. NTPC is executing two other thermal power projects-- the 3x500 MW Jhajjar and the 2x490 MW Dadri extension stage-II-- in the national capital region, to meet the heightened power demand, which is likely to exceed 4,000 MW by October 2010, at the advent of the US$ 17.5 billion event. Similarly, the three units of the Jhajjar project are also likely to be commissioned by July 2010, October 2010 and March 2011, respectively, against their original schedules of October 2010, April 2011 and October 2011.
No comments:
Post a Comment