- The remaining 98 acres of land is also expected to be surrendered shortly, handing the developer control over the entire 2,625 acres identified. Meanwhile, work pertaining to ground leveling and boundary, among others, is also proceeding apace in anticipation of start of construction.
- Pertinently, the notifications necessary for land acquisition, under Sections 4 and 6 of the Land Acquisition Act, were due to be issued back in January 2009, but litigation had hampered the process.
- The UMPP was originally planned to be on steam by September 2013, when the first 800 MW was expected to be operational. Following recent developments, the project is likely to be fully commissioned by February 2015.