During
April 2010, a total of
12 transmission lines and four sub-stations were commissioned in the country. The details of these commissioned transmission assets have been given here.
Transmission lines - --400 kV Sugen -Jhanor D/C line, of 160 Ckm length, in Gujarat.
- --400 kV D/C Ramagundam-Ghanapur line, of 52 Ckm length, at Malkaram in Andhra Pradesh.
- --400 kV D/C and S/C Chabra-Hindaun line, of 342 Ckm length, in Rajasthan.
- --220 kV Versana -Morbi D/C line, of 214 Ckm length, in Gujarat.
- --220 kV Gwalior-Malanpur D/C line, of 17 Ckm length, in Madhya Pradesh.
- --220 kV Jabalpur-Narsinghpur D/C line, of 153 Ckm length, in Madhya Pradesh.
- --220 kV Chegaon-Nimrani D/C line, of 205 Ckm length, in Madhya Pradesh.
- --220 kV Satpura-Itarsi D/C circuit, of 170 Ckm length, in Madhya Pradesh.
- --220 kV Barwaha-Khandwa D/C line, of 4 Ckm length, at Chhegaon new sub-station in Madhya Pradesh.
- --220 kV Indore-Ujjain D/C line, of 2 Ckm length, at Indore sub-station in Madhya Pradesh.
- --220 kV Bhusaval-II-Existing Khandka D/C line, of 15 Ckm length, in Maharashtra.
- --220 kV D/C line from the 400 kV Oglapur sub-station to Nagaram, of 25 Ckm length, in Andhra Pradesh.
Sub-stations
- --400 kV Kirori sub-station of 630 MVA capacity in Haryana.
- --220 kV Lakhani (Agathala) sub-station of 100 MVA capacity in Gujarat.
- --220 kV Botad sub-station of 50 MVA capacity in Gujarat.
- --220 kV Chatarpur sub-station of 160 MVA capacity in Madhya Pradesh.