ALL INDIA INSTALLED CAPACITY

ALL INDIA INSTALLED CAPACITY

Tuesday, April 13, 2010

BHEL commissions 10 projects in 2009-10

  • BHEL synchronized/commissioned 6,583 MW of power plant equipment during the year which includes 5,220 MW for Utility, 634 MW for Captive/Industrial sets and 729 MW in overseas markets. In addition, BHEL was ready for commissioning of 412 MW of hydro power projects and is awaiting critical inputs viz. water / power evacuation system.
  • BHEL also commissioned the 2x220 MW (RAPP Unit V & VI) Non-BHEL nuclear set.
  • A major milestone of the year was the commissioning of four power plants in overseas markets the maximum in a single year. While power projects were commissioned in Bangladesh, Iraq, UAE and Indonesia, substations were commissioned in Afghanistan, Ethiopia and Bangladesh.
  • The installed capacity of BHEL supplied Utility sets went up to 91,481 MW and BHEL maintained its two-third share in the country's total installed capacity.
  • Trombay TPS of TATA Power Company Limited, set up by BHEL on EPC basis, was awarded with the Government of India’s National Award for Early Completion.