Power tariffs are likely to see a 5-7% increase in the next few months if the  proposal to withdraw tax benefits and impose duty on import of equipment for  power plants is accepted.The cost of production for power companies has risen with the government  doubling the price of gas under the administered price mechanism in May.To make matters worse, a proposal to withdraw the 10-year tax holiday for  power plants and impose 19% import duty on power equipment for units with over  1000mw capacity (mega power plants) is under consideration.While the move to dissuade import of power equipment is being taken to  promote the interests of domestic power equipment manufacturers, it is likely to  delay the commissioning of power projects.
The government has set an ambitious target of adding 78,700 mw capacity  during the 11th plan (2007-2012). However, it has managed to add just about  22,000mw so far.Private power players, under the aegis of Association of Power Producers,  have written to the prime minister that levying import duty on power equipment  will force them to increase the power tariffs.
“While we welcome the initiatives the government is considering to encourage  domestic equipment manufacturing, we believe imposing of customs duty has  serious implications on the cost structures and tariffs and can seriously impact  the capacity addition programme being planned by the private sector,” the  association wrote.A committee of secretaries (CoS) had on July 12 passed the proposal of  levying import duty on the imported equipment for power plants.
While a report prepared by Planning Commission member Arun Maira had proposed  only 14% import duty on imported equipment, the CoS headed by cabinet secretary  KM Chandrashekhar increased the duty by 19% in its final decision.If the cabinet approves the decision of CoS then the imported power equipment  will attract a 5% customs duty, 10% countervailing duty and 4% special  additional duty.
Domestic power companies have placed orders for overseas equipment to  generate 26,000mw annually because of the slow delivery cycle of local  manufacturers to meet growing demand.Rupesh Sankhe, an analyst with of Angel Broking said imported power plants  from China are relatively cheaper.“While the per-megawatt cost of completion of a thermal power project using  Chinese equipment is around Rs3.5-4 crore, it works out to Rs4.5-5 crore for  projects using equipment from elsewhere,” Sankhe wrote.“An increase in import duty will force the developers to increase their power  tariffs by 5-7%,” Sankhe added.
Arun Srivastava, executive director, infrastructure & government  advisory, Ernst and Young, with power producers entering into long-term power  purchasing agreements, mid way policy changes by the government hurt.“The foreign companies have a shorter delivery cycle. If the import of  foreign equipment is discouraged, it will increase the time required to set up  power plant by around 2-8 months,” Srivastava added.

No comments:
Post a Comment