To stick to its original schedule for the supply of CC-pumps, BHEL had, earlier, committed to air lift these pumps from the original equipment manufacturer (OEM), which is based in Japan. However, the state run equipment major finally had to resort to the sea-route for shipping the equipment. Further, issues with the supply of IP turbine inner casing are affecting the commissioning schedule of
units 2 and 3, as well. The project, being developed by Aravali Power Company Private Limited,
a joint venture between NTPC, Indraprastha Power Generation Corporation Private Limited (IPGCPL) and Haryana Power Generation Corporation Limited (HPGCL), was expected to meet part of the power needs of the impending commonwealth games; however, BHEL`s lapses have rendered this a remote possibility.